KNTV-TV

Mar 1, 2006 12:00 PM

    

Winner of RF systems

SUBMITTED BY THALES BROACAST & MULTIMEDIA

KNTV served the Salinas and Monterey, CA, markets for 45 years from Loma Prieta Mountain. In 2001, KNTV switched to cover the San Jose, San Francisco and Oakland DMA. In order to improve coverage, the station decided to move the transmitter location to San Bruno Mountain.

Although KNTV's tower site was an existing facility on a mountaintop near the San Francisco airport, there were both FAA and environmental concerns due to the fact that the tower height was being increased by 57ft. It took three and a half years of planning, petitions, hearings and legal motions that added challenge, time and cost to this project.

Besides monitoring, there is only 30ft of analog signal path between the DA converters and the transmitter inputs. KNTV's new transmitter site was designed to be as reliable as possible, with all systems configured as dual and most as hot standby. The Thales OPTIMUM solid-state VHF NTSC and DTV parallel transmitters satisfied this need. Liquid cooling offered the station two important benefits. The transmitter cabinets are physically smaller because there are no air plenums. They also help reduce operating expenses because heat energy is transferred outside the building, minimizing the requirement for building cooling systems.

The transmitter facility was remodeled to the extreme with construction and project management services provided by McCormick Construction. The existing 35ft × 35ft cement block building was completely stripped before the new construction proceeded. A new roof, new electrical, new flooring, new HVAC, new security system and water storage systems completed the building upgrade. A total upgrade to current seismic code for both the building and the tower were completed. In addition, the existing tower was stripped, and the top 110ft was replaced with new steel before the new Dielectric antennas and transmission line were installed. A new grounding system was required to protect all the solid-state hardware from lightning strikes. SAE designed and installed a special grounding system that provides 5Ω to ground from anywhere on the site.

Emergency power for the site's entire load was installed, including a new UPS, automatic transfer switch, diesel generator and fuel storage system. GE provided a kinetic energy UPS system with sufficient capacity to keep KNTV on-air during any momentary power bumps or surges. The emergency power system is fully automatic with adequate fuel storage to keep the site on-air at full power for up to seven days.

Runner-up: WCJB-TV

SUBMITTED BY AXCERA

Technology at work: Axcera Visionary HP80DAW NTSC transmitter and Innovator DT-LDU2A-8 DTV transmitter; Dielectric filters and combiners, transmission line and antenna; MYAT filters and combiners.




Want to use this article?
Click here for options!
Get Copyright Clearance

Share this article

blog comments powered by Disqus

 

Brad on Broadcast


Tell us how you use social media in your job!
You could win 1 of 4 iTunes gift cards for your participation.

Current Issue

Online captioning compliance

May 2012

The FCC has issued captioning requirements for all online video. Learn how to meet the requirements of the new rules and how to automate the technical process.

Read More articles...


Recent Comments

Powered by Disqus

 


Video Compression, Editing and Displays

Video Compression, Editing and Displays

Video compression, editing and displays is an in-depth tutorial on MPEG compression technology, editing MPEG content and evaluating color video monitors written by long-time video expert, trainer and writer Steve Mullen, Ph. D.

File Based Technology and Workflow

File Based Technology and Workflow

File-based technologies have replaced video tape methods for a majority of production and broadcast operations. The worlds of AV and IT are coalescing to create new methods and workflows for media

Sound Off Podcasts

 

Broadcast Engineering Digital Reference Guide

Browse Back Issues

Back to Top