Sprint Nextel reports continued progress on 2GHz BAS relocation project

Aug 15, 2008 8:00 AM


         Subscribe in NewsGator Online   Subscribe in Bloglines
Engineers accessing towers and buildings atop Slide Mountain near Reno, NV, to do a site survey for BAS relocation work in May found them buried beneath 10ft of snow and ice.

Engineers accessing towers and buildings atop Slide Mountain near Reno, NV, to do a site survey for BAS relocation work in May found them buried beneath 10ft of snow and ice.

The latest report to the FCC from Sprint Nextel shows continued progress on the relocation effort to move Broadcast Auxiliary Service (BAS) licensees to new 12MHz-wide digital channel assignments in the 2GHz band.

In a letter dated Aug. 1 to the commission, Sprint Nextel reported that 91 percent of 968 primary BAS broadcasters eligible for relocation have executed frequency relocation agreements (FRAs) with the company. Additionally, 99 percent of those broadcasters have submitted quote packages for the equipment and services necessary to make the transition.

As in the last update to the commission, Sprint Nextel pointed out that it, along with many of the BAS incumbents, have experienced challenging circumstances in executing the FCC mandate to complete the transition. For example, broadcasters in Reno, NV, use towers atop Slide Mountain, 10,000ft above sea level. When crews attempted to do a site survey of the facilities on the mountain in May, which were only accessible via snowcat, they found buildings, towers and cable troughs buried in 10ft of snow and ice. As a result, work was postponed for a later date when conditions had improved, delaying the successful transition of the market until July 30.

The company also pointed to a few other noteworthy accomplishments since its last update submitted to the commission in June. Specifically, the Columbus, GA, market has completed its transition ahead of schedule and BAS licensees in the Tampa-St. Petersburg, FL, DMA completed their transition in mid-July.

The Tampa transition was especially demanding given the number of BAS licensees and amount of equipment in the market. According to the company, transitioning the market required replacing equipment in 34 electronic newsgathering (ENG) trucks, four helicopters and dozens of fixed and portable microwave links.

Sprint Nextel also reported that its efforts to accelerate the 2GHz BAS transition in markets where Mobile Satellite Service (MSS) operators, which will take over some of the spectrum freed up by the transition, have requested expedited action are making progress. Fourteen of the 25 markets where MSS licensees Terrestar and ICO have requested the BAS transition be accelerated have completed their relocation. Additionally, all broadcast incumbents in the 11 remaining high-priority markets have submitted signed FRAs and submitted purchase orders for replacement RF equipment and services.


Commenting terms of use blog comments powered by Disqus

Want to use this article?
Click here for options!
Get Copyright Clearance

--->

Related Newsletter

News Technology Update
A twice-monthly newsletter covering the equipment used to produce the news.

Confused about the termnology in an article? Find definitions of common terms and abbreviations in Broadcast Engineering's Glossary.

 

Browse Back Issues

Resources

Broadcast Engineering Newsletters Broadcast Engineering Essential Guides Broadcast Engineering White Papers Broadcast Engineering Videos Broadcast Engineering Podcasts Broadcast Engineering Buyers Guide Broadcast Engineering Industry Calendar

Industry Calendar

Broadcast Engineering Glossary of Terms

Glossary

Broadcast Engineering RSS feed

RSS

Interactive Media

Broadcast Engineering Webinars Broadcast Engineering Training Broadcast Engineering Blogs Broadcast Engineering Forums Broadcast Engineering JobZone

JobZone

Broadcast Engineering BE Roll

Blog

 

Back to Top